Arkansas State Guide โ€” Updated 2026

Arkansas Demolition Permit
Requirements

๐Ÿ›๏ธ
Arkansas Permits Are Issued Locally
Arkansas does not have a statewide demolition permit. Local building departments issue all permits. For asbestos NESHAP notification, contact: ADEQ, Air Division, Asbestos Program: 501-682-0744

Permit Structure and Fees

Demolition permits in Arkansas are issued by your local city or county building department. Typical residential permit fees range from $50โ€“$150. Contact your local building department for the current application process, required documents, and fees.

Key Arkansas Requirements

ADEQ handles asbestos NESHAP. Local permits issued by municipalities. Arkansas has no statewide general contractor licensing for demolition.

Asbestos Notification in Arkansas

The 10-working-day advance asbestos NESHAP notification for demolitions that disturb regulated asbestos-containing material (RACM) above threshold amounts must be submitted to: ADEQ, Air Division, Asbestos Program: 501-682-0744

Standard RACM thresholds: 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet removed. For any structure built before 1980, schedule a licensed asbestos inspection before applying for your permit. See our full asbestos inspection guide for what this involves and what it costs.

Pre-Demolition Checklist for Arkansas Projects

  • Confirm permit requirement with local building department
  • Schedule asbestos inspection for pre-1980 structures
  • Submit NESHAP notification if RACM exceeds thresholds (to: ADEQ, Air Division, Asbestos Program: 501-682-0744)
  • Arrange utility disconnections: gas, electric, water, sewer
  • Submit demolition permit application with all required documents
  • Post permit on-site; complete demolition; schedule final inspection

Download our free Pre-Demolition Checklist PDF covering all steps in sequence.

Arkansas Demolition FAQs

Who handles asbestos notification in Arkansas?+

Asbestos NESHAP notification for Arkansas demolition projects goes to: ADEQ, Air Division, Asbestos Program: 501-682-0744. The 10-working-day notice is required before demolition when RACM exceeds 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet of removed material. See our asbestos guide for full details on the notification process.

What does a demolition permit cost in Arkansas?+

Demolition permit fees in Arkansas typically range from $50โ€“$150 for residential structures. This covers the permit fee only โ€” asbestos inspection ($250โ€“$800), utility disconnection ($200โ€“$1,000), and debris disposal are additional costs. See our complete cost guide for a full breakdown.

Do I need a permit to demolish a shed in Arkansas?+

It depends on your local jurisdiction. Many Arkansas cities and counties exempt sheds under 120โ€“200 square feet from demolition permit requirements. Larger sheds, and any shed with utility connections, typically require a permit. Contact your local building department to confirm the specific threshold for your area. See our permit trigger guide for the full framework.

Disclaimer: Arkansas demolition permit requirements vary by local jurisdiction. Always confirm with your local building department before beginning any demolition work.