Georgia State Guide โ€” Updated 2026

Georgia Demolition Permit
Requirements

๐Ÿ›๏ธ
Georgia: Local Permits โ€” State Environmental Agency for Asbestos
Georgia does not have a statewide demolition permit. Local building departments issue all permits. The state environmental agency handles asbestos NESHAP notification: Georgia DNR, Environmental Protection Division (EPD), Air Protection Branch: 404-363-7000

Permit Structure in Georgia

Demolition permits in Georgia are issued by your local city or county building department. Requirements and fees vary by jurisdiction. Typical residential permit fees in Georgia range from $100โ€“$400. Contact your local building department for current requirements and application procedures.

Georgia EPD 7-calendar-day state notice (federal 10 working days also applies). Fulton County requires licensed contractor for residential structural demolition. Historic structures in Savannah's historic district require Historic Review Board approval.

Asbestos Notification: Georgia

Georgia's state asbestos rule requires 7 calendar days advance notice โ€” shorter than the federal 10 working days. The federal 10-working-day requirement also applies; in practice, submit as early as possible. Georgia EPD accepts electronic notification.

The standard NESHAP 10-working-day advance notification applies when RACM exceeds 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet of material removed from components. Submit to the agency listed above well in advance of your project start date.

Typical Permit Process in Georgia

1
Confirm Permit Requirement
Contact your local building department. Most structures require a permit; small sheds may be exempt depending on local thresholds.
2
Schedule Asbestos Inspection
For any structure built before 1980, hire an AHERA-accredited asbestos inspector. The inspection report is required with your permit application.
3
Submit NESHAP Notification (If Required)
If RACM exceeds threshold amounts, submit the 10-working-day advance notification to: Georgia DNR, Environmental Protection Division (EPD), Air Protection Branch: 404-363-7000
4
Disconnect Utilities
Arrange disconnection of gas, electric, water, and sewer. Obtain written confirmation from each utility. This is required before a permit will issue.
5
Apply for Demolition Permit
Submit your application to your local building department with all required documentation. Permit fees in Georgia: $100โ€“$400.
6
Post Permit, Demo, Final Inspection
Post the issued permit on-site, complete demolition, schedule final inspection to close the permit and create the legal record of removal.

Georgia Demolition FAQs

Does Georgia have a statewide demolition permit?+

No. Georgia does not issue a statewide demolition permit. All permits are issued by local city or county building departments under local building codes. The state environmental agency handles asbestos notification (Georgia DNR, Environmental Protection Division (EPD), Air Protection Branch: 404-363-7000), but the actual demolition permit is a local document.

Who handles asbestos notification in Georgia?+

Georgia's state asbestos rule requires 7 calendar days advance notice โ€” shorter than the federal 10 working days. The federal 10-working-day requirement also applies; in practice, submit as early as possible. Georgia EPD accepts electronic notification. Contact the agency at the number listed above for current notification forms and procedures.

What is the typical cost of a demolition permit in Georgia?+

Demolition permit fees in Georgia typically range from $100โ€“$400 for residential structures. This is the permit fee only โ€” asbestos inspection ($250โ€“$800), utility disconnection ($200โ€“$1,000), and other pre-demolition costs are separate. See our full cost guide for a complete breakdown.

Disclaimer: Georgia demolition permit requirements vary by local jurisdiction. Always confirm with your local building department before beginning demolition work.