Georgia Demolition Permit
Requirements
Permit Structure in Georgia
Demolition permits in Georgia are issued by your local city or county building department. Requirements and fees vary by jurisdiction. Typical residential permit fees in Georgia range from $100โ$400. Contact your local building department for current requirements and application procedures.
Georgia EPD 7-calendar-day state notice (federal 10 working days also applies). Fulton County requires licensed contractor for residential structural demolition. Historic structures in Savannah's historic district require Historic Review Board approval.
Asbestos Notification: Georgia
Georgia's state asbestos rule requires 7 calendar days advance notice โ shorter than the federal 10 working days. The federal 10-working-day requirement also applies; in practice, submit as early as possible. Georgia EPD accepts electronic notification.
The standard NESHAP 10-working-day advance notification applies when RACM exceeds 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet of material removed from components. Submit to the agency listed above well in advance of your project start date.
Typical Permit Process in Georgia
Georgia Demolition FAQs
Does Georgia have a statewide demolition permit?+
No. Georgia does not issue a statewide demolition permit. All permits are issued by local city or county building departments under local building codes. The state environmental agency handles asbestos notification (Georgia DNR, Environmental Protection Division (EPD), Air Protection Branch: 404-363-7000), but the actual demolition permit is a local document.
Who handles asbestos notification in Georgia?+
Georgia's state asbestos rule requires 7 calendar days advance notice โ shorter than the federal 10 working days. The federal 10-working-day requirement also applies; in practice, submit as early as possible. Georgia EPD accepts electronic notification. Contact the agency at the number listed above for current notification forms and procedures.
What is the typical cost of a demolition permit in Georgia?+
Demolition permit fees in Georgia typically range from $100โ$400 for residential structures. This is the permit fee only โ asbestos inspection ($250โ$800), utility disconnection ($200โ$1,000), and other pre-demolition costs are separate. See our full cost guide for a complete breakdown.