Idaho State Guide โ€” Updated 2026

Idaho Demolition Permit
Requirements

๐Ÿ›๏ธ
Idaho Permits Are Issued Locally
Idaho does not have a statewide demolition permit. Local building departments issue all permits. For asbestos NESHAP notification, contact: Idaho DEQ, Air Quality Division, Asbestos: 208-373-0550

Permit Structure and Fees

Demolition permits in Idaho are issued by your local city or county building department. Typical residential permit fees range from $50โ€“$150. Contact your local building department for the current application process, required documents, and fees.

Key Idaho Requirements

Idaho DEQ handles asbestos NESHAP. Local permits issued by cities and counties. Ada County and Canyon County issue own permits. Idaho has no statewide general contractor licensing.

Asbestos Notification in Idaho

The 10-working-day advance asbestos NESHAP notification for demolitions that disturb regulated asbestos-containing material (RACM) above threshold amounts must be submitted to: Idaho DEQ, Air Quality Division, Asbestos: 208-373-0550

Standard RACM thresholds: 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet removed. For any structure built before 1980, schedule a licensed asbestos inspection before applying for your permit. See our full asbestos inspection guide for what this involves and what it costs.

Pre-Demolition Checklist for Idaho Projects

  • Confirm permit requirement with local building department
  • Schedule asbestos inspection for pre-1980 structures
  • Submit NESHAP notification if RACM exceeds thresholds (to: Idaho DEQ, Air Quality Division, Asbestos: 208-373-0550)
  • Arrange utility disconnections: gas, electric, water, sewer
  • Submit demolition permit application with all required documents
  • Post permit on-site; complete demolition; schedule final inspection

Download our free Pre-Demolition Checklist PDF covering all steps in sequence.

Idaho Demolition FAQs

Who handles asbestos notification in Idaho?+

Asbestos NESHAP notification for Idaho demolition projects goes to: Idaho DEQ, Air Quality Division, Asbestos: 208-373-0550. The 10-working-day notice is required before demolition when RACM exceeds 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet of removed material. See our asbestos guide for full details on the notification process.

What does a demolition permit cost in Idaho?+

Demolition permit fees in Idaho typically range from $50โ€“$150 for residential structures. This covers the permit fee only โ€” asbestos inspection ($250โ€“$800), utility disconnection ($200โ€“$1,000), and debris disposal are additional costs. See our complete cost guide for a full breakdown.

Do I need a permit to demolish a shed in Idaho?+

It depends on your local jurisdiction. Many Idaho cities and counties exempt sheds under 120โ€“200 square feet from demolition permit requirements. Larger sheds, and any shed with utility connections, typically require a permit. Contact your local building department to confirm the specific threshold for your area. See our permit trigger guide for the full framework.

Disclaimer: Idaho demolition permit requirements vary by local jurisdiction. Always confirm with your local building department before beginning any demolition work.