Montana State Guide โ€” Updated 2026

Montana Demolition Permit
Requirements

๐Ÿ›๏ธ
Montana Permits Are Issued Locally
Montana does not have a statewide demolition permit. Local building departments issue all permits. For asbestos NESHAP notification, contact: MT DEQ, Air Resources Management Division: 406-444-3490

Permit Structure and Fees

Demolition permits in Montana are issued by your local city or county building department. Typical residential permit fees range from $50โ€“$150. Contact your local building department for the current application process, required documents, and fees.

Key Montana Requirements

MT DEQ handles asbestos NESHAP. Local permits issued by cities and counties. Many rural Montana areas have no formal local permit requirement but NESHAP still applies.

Asbestos Notification in Montana

The 10-working-day advance asbestos NESHAP notification for demolitions that disturb regulated asbestos-containing material (RACM) above threshold amounts must be submitted to: MT DEQ, Air Resources Management Division: 406-444-3490

Standard RACM thresholds: 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet removed. For any structure built before 1980, schedule a licensed asbestos inspection before applying for your permit. See our full asbestos inspection guide for what this involves and what it costs.

Pre-Demolition Checklist for Montana Projects

  • Confirm permit requirement with local building department
  • Schedule asbestos inspection for pre-1980 structures
  • Submit NESHAP notification if RACM exceeds thresholds (to: MT DEQ, Air Resources Management Division: 406-444-3490)
  • Arrange utility disconnections: gas, electric, water, sewer
  • Submit demolition permit application with all required documents
  • Post permit on-site; complete demolition; schedule final inspection

Download our free Pre-Demolition Checklist PDF covering all steps in sequence.

Montana Demolition FAQs

Who handles asbestos notification in Montana?+

Asbestos NESHAP notification for Montana demolition projects goes to: MT DEQ, Air Resources Management Division: 406-444-3490. The 10-working-day notice is required before demolition when RACM exceeds 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet of removed material. See our asbestos guide for full details on the notification process.

What does a demolition permit cost in Montana?+

Demolition permit fees in Montana typically range from $50โ€“$150 for residential structures. This covers the permit fee only โ€” asbestos inspection ($250โ€“$800), utility disconnection ($200โ€“$1,000), and debris disposal are additional costs. See our complete cost guide for a full breakdown.

Do I need a permit to demolish a shed in Montana?+

It depends on your local jurisdiction. Many Montana cities and counties exempt sheds under 120โ€“200 square feet from demolition permit requirements. Larger sheds, and any shed with utility connections, typically require a permit. Contact your local building department to confirm the specific threshold for your area. See our permit trigger guide for the full framework.

Disclaimer: Montana demolition permit requirements vary by local jurisdiction. Always confirm with your local building department before beginning any demolition work.