South Carolina State Guide โ€” Updated 2026

South Carolina Demolition Permit
Requirements

๐Ÿ›๏ธ
South Carolina Permits Are Issued Locally
South Carolina does not have a statewide demolition permit. Local building departments issue all permits. For asbestos NESHAP notification, contact: SCDHEC, Air Quality Bureau, Asbestos Program: 803-898-4123

Permit Structure and Fees

Demolition permits in South Carolina are issued by your local city or county building department. Typical residential permit fees range from $75โ€“$250. Contact your local building department for the current application process, required documents, and fees.

Key South Carolina Requirements

SCDHEC administers asbestos NESHAP. Local permits issued by municipalities and counties. Charleston historic district requires BAR (Board of Architectural Review) approval for demolitions.

Asbestos Notification in South Carolina

The 10-working-day advance asbestos NESHAP notification for demolitions that disturb regulated asbestos-containing material (RACM) above threshold amounts must be submitted to: SCDHEC, Air Quality Bureau, Asbestos Program: 803-898-4123

Standard RACM thresholds: 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet removed. For any structure built before 1980, schedule a licensed asbestos inspection before applying for your permit. See our full asbestos inspection guide for what this involves and what it costs.

Pre-Demolition Checklist for South Carolina Projects

  • Confirm permit requirement with local building department
  • Schedule asbestos inspection for pre-1980 structures
  • Submit NESHAP notification if RACM exceeds thresholds (to: SCDHEC, Air Quality Bureau, Asbestos Program: 803-898-4123)
  • Arrange utility disconnections: gas, electric, water, sewer
  • Submit demolition permit application with all required documents
  • Post permit on-site; complete demolition; schedule final inspection

Download our free Pre-Demolition Checklist PDF covering all steps in sequence.

South Carolina Demolition FAQs

Who handles asbestos notification in South Carolina?+

Asbestos NESHAP notification for South Carolina demolition projects goes to: SCDHEC, Air Quality Bureau, Asbestos Program: 803-898-4123. The 10-working-day notice is required before demolition when RACM exceeds 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet of removed material. See our asbestos guide for full details on the notification process.

What does a demolition permit cost in South Carolina?+

Demolition permit fees in South Carolina typically range from $75โ€“$250 for residential structures. This covers the permit fee only โ€” asbestos inspection ($250โ€“$800), utility disconnection ($200โ€“$1,000), and debris disposal are additional costs. See our complete cost guide for a full breakdown.

Do I need a permit to demolish a shed in South Carolina?+

It depends on your local jurisdiction. Many South Carolina cities and counties exempt sheds under 120โ€“200 square feet from demolition permit requirements. Larger sheds, and any shed with utility connections, typically require a permit. Contact your local building department to confirm the specific threshold for your area. See our permit trigger guide for the full framework.

Disclaimer: South Carolina demolition permit requirements vary by local jurisdiction. Always confirm with your local building department before beginning any demolition work.