Free Printable Checklist

Pre-Demolition
Permit Checklist

Every required step in sequence โ€” from permit confirmation through final inspection. Print this page or use it on-screen as you work through the process.

โšก Check My Permit Requirement
Phase 1 โ€” Before You Apply (Weeks 1โ€“3)
Day 1
Confirm permit requirement with local building department Call or visit your city/county building dept. Ask: "Is a demolition permit required for [structure type] at [address]?" Get the answer in writing if possible. Ask for the required documents list.
Day 1
Check historic designation status Verify whether the property is in a local historic district, state historic register, or National Register. Local landmark designations can block or significantly delay demolition. Check before committing to a demolition timeline.
Day 1โ€“3
Schedule asbestos inspection (pre-1980 structures) Hire an AHERA-accredited asbestos inspector. Inspection takes 1โ€“3 days on-site; lab results take 3โ€“10 business days. Cost: $250โ€“$800. Most building departments require the inspection report with the permit application. Do not skip this step for any structure built before 1980.
Day 1
Contact all utilities to schedule disconnection Start all utilities simultaneously, not sequentially: gas company, electric utility, water department, sewer district, and telecom providers (cable, phone, internet). Each has its own scheduling lead time. Underground gas service can take 15โ€“25 business days if a street opening permit is required.
Day 5โ€“10
Receive asbestos inspection report Confirm the report includes: all suspect materials identified, sampling locations documented, lab results (PLM analysis), and inspector's RACM classification. If RACM is found, schedule licensed abatement contractor before proceeding.
Day 5โ€“10
Submit NESHAP asbestos notification (if RACM present above thresholds) Submit 10-working-day advance notice to your state asbestos agency (or EPA Region 1 for VT and RI). Required when RACM exceeds: 260 linear feet on pipes, 160 sq ft on other components, or 35 cubic feet removed. The 10-day clock starts when the agency receives a COMPLETE notification โ€” not when you mail it.
Days 5โ€“20
Complete asbestos abatement (if RACM found) Licensed abatement contractor must remove and dispose of all RACM before demolition begins. Abatement contractor provides a clearance air monitoring report after work is complete. This report becomes part of your permit application package.
Days 5โ€“20
Obtain utility disconnection sign-offs Get written confirmation from each utility: gas disconnect/cap, electric meter removal, water curb-stop shutoff, sewer lateral cap (requires licensed plumber + plumbing permit in most jurisdictions). Collect all stickers, work orders, or disconnect letters for your permit application.
Phase 2 โ€” Permit Application
Week 3
Assemble complete permit application package Typical required documents: completed application form, proof of property ownership, asbestos inspection report (or exemption documentation), utility disconnection confirmations, contractor license information (if required), site/grading plan (if required by jurisdiction).
Week 3
Submit demolition permit application and pay fee Submit to your local building department โ€” online portal or in person. Typical fee: $75โ€“$500 for residential. Confirm the refund policy before paying. Some jurisdictions are non-refundable regardless of whether work proceeds.
Weeks 3โ€“5
Respond promptly to any deficiency notices If the building department requests additional documents or corrections, respond within their stated deadline. Failing to respond restarts the review clock and may result in permit denial.
Week 4โ€“6
Receive issued demolition permit Do not begin demolition before the permit is issued โ€” not just submitted. Starting work before permit issuance is treated the same as working without a permit.
Phase 3 โ€” Demolition and Close-Out
Demo Day
Post permit visibly on-site before work begins The issued permit must be posted in a visible location on the property during all demolition work. Keep a copy in a safe location โ€” you will need it for the final inspection and when you sell the property.
Demo Day
Confirm 811 "Call Before You Dig" is completed Call 811 (the national underground utility notification service) before any excavation or demolition that involves digging. Required in all 50 states. Underground utility strikes during unpermitted or un-notified work create serious safety and liability risks.
During Demo
Stop work immediately if unexpected asbestos is discovered Notify the contractor and your state asbestos agency immediately. Do not disturb the material further. Arrange for additional sampling and abatement before resuming. Continuing demolition after unexpected asbestos discovery is a serious NESHAP violation.
After Demo
Obtain debris disposal documentation Request weight tickets from the C&D disposal facility for all debris loads. These document legal disposal and protect you as the waste generator if disposal practices are later questioned.
After Demo
Grade and seed the site as required by permit Some demolition permits require the site to be graded to a specific final elevation and seeded or stabilized within a set time after demolition. Confirm these conditions in your permit before closing out.
Week 6โ€“8
Schedule and pass final site inspection Contact your building department to schedule the final inspection. The inspector confirms: utilities are capped, debris is cleared, and the site is graded appropriately. Keep the signed-off inspection report โ€” it is your legal proof that the demolition was completed under permit.
After Inspection
Confirm permit is officially closed in building department records After the final inspection, verify that the permit status shows "Closed" or "Final" in the building department's online permit portal. This is the record that future title searches will find when you sell the property. Save a copy of the closed permit for your files.
Disclaimer: This checklist provides general informational guidance on the demolition permit process and is not legal or professional advice. Requirements vary by jurisdiction. Always confirm current requirements with your local building department and state environmental agency before beginning any demolition project. ResidentialDemolition.pages.dev โ€” free informational reference only.